Things flowing smoothly with the Big Pipe Project

2012 will be the first full year in Portland’s history that we are not using the Willamette River as a default sewer. Completing the CSO Program last month should dramatically alter the way Portlanders view our river and interact with it.The Bureau of Environmental Services not only came under budget but met its December 2011 deadline to complete the 20-year program to control combined sewer overflows (CSOs) to the Willamette River and Columbia Slough. An Oregon Department of Environmental Quality (DEQ) order, originally issued in 1991 and amended in 1994, required the city to control CSOs by December 1, 2011. Completing the CSO program reduces stormwater overflow events from an average of 50 per year to an average of four each winter, and just one every third